Each card is a real improvement: how it looked before, what was wrong, and the result after the change.

Troubleshooting WIP control (sample) – After
Troubleshooting WIP control (sample) – Before
BeforeAfter
⟷

01 Oct 2026 · Troubleshooting Department

Troubleshooting WIP control (sample)

What was wrong
WIP stood at 480 PCS, above the 300 PCS ceiling. Waiting, in-rework and finished lots shared one area, and with no traveler slip it was hard to trace board ID, defect and owner.
Result
7-day target: WIP ≤ 300 PCS. Three marked zones with signage, a mandatory traveler per lot, WIP board updated twice per shift, rework lead time ≤ 2 days.